WHAT IS DEMAND FORECASTING?
- Definition Calculating the future demand in advance by using scientific and statistical method based on demand history data
- Characteristics
- ① Forecasting methods assume that the causal relations in the past continue to exist in the future
- ② There can be always errors in forecasting
- ③ Group basis forecast is more accurate than individual forecast
- ④ Accuracy of forecast lowers as forecasting term increases
- ⑤ There is no forecasting method that predicts exact random variation
- Variation Factors of Forecast
- ① Trend
- ② Consistent incline or decline over time
- ③ Seasonality
- ④ Repeated high demand in a specific season annually
- ⑤ Cyclical Variation
- ⑥ Show a repetitive demand pattern at a certain period
- ⑦ Random Variation (Unpredictable)
- ⑧ Caused by unknown or random factor
INPUTS & OUTPUTS
Text from figure
Demand History · Monthly Average
EMD
Demand Forecast System
Technology Information · Safety Stock
Before / After Part
ITC
TRENDS COMPONENT
Cyclic and long term variation which shows increases or decreases in trend continuously.
Text from figure
Term
CYCLICAL COMPONENT
Difficult to forecast because of irregularity of the cycle and amplitude. Need to check and forecast at which point the present phase is in the cycle.
Text from figure
Trend
Term
SEASONAL COMPONENT
Variation of demand regularly occurs during the year, and is caused by the systematic and natural factors like weather, traditions, customs, etc.
Term
RANDOM VARIATION
Shows no fixed forms (unpredictable)
Text from figure
Trend
Term
DEMAND FORECASTING MODELS
- 3 Months Moving Average Simplest Model Suitable for short term forecasting for stable demand
Text from figure
Predictable Error
m - 3
1
×ΣAj
EMDm =>
3
j = m - 1
Applicability : Demand displays no trend or seasonality
e.g.
| Month | Jan. | Feb. | Mar. | Apr. | May. | Jun. |
|---|---|---|---|---|---|---|
| Demand | 3 | 4 | 5 | 4 | 6 | 5 |
EMD of July = (4 + 6 + 5) / 3 = 5
- 6 Months Moving Average
Text from figure
Predictable Error
m - 6
1
×ΣAj
EMDm =>
6
j = m - 1
Applicability : Demand displays no trend or seasonality
e.g.
| Month | Jan. | Feb. | Mar. | Apr. | May. | Jun. |
|---|---|---|---|---|---|---|
| Demand | 5 | 4 | 5 | 3 | 6 | 5 |
EMD of July = (5 + 4 + 7 + 3 + 6 + 5) / 6 = 5
- 6 Months Median
Text from figure
Predictable Error
EMDm => A(n+1)/2 · if n is odd
1
EMDm => · × (An/2+ A(n/2)+1) · if n is even
2
Applicability : Demand displays no trend or seasonality
e.g.
| Month | Jan. | Feb. | Mar. | Apr. | May. | Jun. |
|---|---|---|---|---|---|---|
| Demand | 6 | 4 | 8 | 5 | 10 | 9 |
EMD of July = Median(4, 5, 6, 8, 9, 10) = (6 + 8) / 2 = 7